L
lbailyn
I am trying to use the project web access updates to update my project schedule using a test project before we roll out server on our projects. We're using server 2003
When a resource updates the percent complete on a task to 100%, and I use the update progress in project professional to accept the updates, it marks the task as complete on the originally scheduled dates, even if the resource finishes the task early or late. I've tried changing the calculation options that relate to the status date as I thought that would solve the problem, but it didn't. What I want to be happen is that the actual dates change so that they are correct, and that should then impact the schedule for successor tasks
help
Thanks
Lauren Bailyn
When a resource updates the percent complete on a task to 100%, and I use the update progress in project professional to accept the updates, it marks the task as complete on the originally scheduled dates, even if the resource finishes the task early or late. I've tried changing the calculation options that relate to the status date as I thought that would solve the problem, but it didn't. What I want to be happen is that the actual dates change so that they are correct, and that should then impact the schedule for successor tasks
help
Thanks
Lauren Bailyn