How does one assure getting the most accurate actual numbers in
Project Professional 2003?
We had a bit of an alarm this morning. Online view of a project
showed that actuals exceeded baseline by $4,000.00 and we have 1300
hours remaining on the Project.
I saved to a mpp file offline and now see more realistic and less
alarming numbers: Actuals $8,000 less than baseline, and about 300
less hours of remaining work.
Anybody else run into difficulties looking at numbers in the
Professional client?
Anybody have a best practice for procedures to perform before
reporting that will assure accurate results?
Project Professional 2003?
We had a bit of an alarm this morning. Online view of a project
showed that actuals exceeded baseline by $4,000.00 and we have 1300
hours remaining on the Project.
I saved to a mpp file offline and now see more realistic and less
alarming numbers: Actuals $8,000 less than baseline, and about 300
less hours of remaining work.
Anybody else run into difficulties looking at numbers in the
Professional client?
Anybody have a best practice for procedures to perform before
reporting that will assure accurate results?