ProjectNewbie
Can anybody out there think of a reason why MS Project would manipulate the
actual hours as recorded by resources?
For example, John Doe fills out his timesheet on Project Web Access for a
week's worth of work to a task, and records the following hours for Task A:
M: 4
T: 2
W: 1
T: 3
F: 5
I accept and update John's time, and somehow, this appears like this in the
Project Plan's Actual Work fields for that task:
M: 3.34
T: 2.56
W: .98
T: 2.79
F: 5.33
The week totals are correct, but the daily hours do not match what the
resource submitted and what I approved.
I'm stumped.
actual hours as recorded by resources?
For example, John Doe fills out his timesheet on Project Web Access for a
week's worth of work to a task, and records the following hours for Task A:
M: 4
T: 2
W: 1
T: 3
F: 5
I accept and update John's time, and somehow, this appears like this in the
Project Plan's Actual Work fields for that task:
M: 3.34
T: 2.56
W: .98
T: 2.79
F: 5.33
The week totals are correct, but the daily hours do not match what the
resource submitted and what I approved.
I'm stumped.