Active tasks over time

G

Gary Johnson

Hi,

I need to plot the number of active tasks against time for an individual
project. This should then provide an "exponential curve" detailing how many
tasks are active. All I am interested in is if there are 35 active tasks
this week and two were completed before next week then the total active
tasks would drop by two for next week.

Can anyone help ?

Thanks

Gary
 
J

Jan De Messemaeker

Hi Gary,

Best is to look at which tasks have Work greater than zero during the wek.
This can be done with the Timescaledata method.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
G

Gérard DUCOURET

Hello Gary
If you want, I can send you a VBA procedure (mpp file) which lists all the tasks which are active
during a specific period of time.

Gérard Ducouret
 
G

Gary Johnson

Hello Gérard

That would be fantastic - please send to (e-mail address removed)

I am very grateful.

Thank you.

Gary Paxman
 
G

Gérard DUCOURET

I sent it to your email address. Tell me if you have any problem to use it.

Gérard Ducouret
 