Actual Cost

R

RandyK

I have a few projects with tasks that have values in Work / Actual Work /
Actual Work Protected. The "Cost" column looks okay - however "Actual
Cost" and "ACWP" columns are all zero's (0). I've checked the resource rate
tables - they seem fine and I have tried republsihing the project plan.
Any idea why this would be occuring?
 
Top