C
CQ
After my users update and the Project Mnager accepts them. The ACTUAL finish
date is always being populated with the originally scheduled finish date. As
an example, if I had a task with a finish date of 8/24/05 and the person
finishes it on 9/1/5, I would expect the ACTUAL finish date to be 9/1/5.
However, it shows up as 8/24/5. How do I correct this?
date is always being populated with the originally scheduled finish date. As
an example, if I had a task with a finish date of 8/24/05 and the person
finishes it on 9/1/5, I would expect the ACTUAL finish date to be 9/1/5.
However, it shows up as 8/24/5. How do I correct this?