S
Steve
What reasons are there that the actual hours is being calculated to be
inhuman hours (.28, 3.87, 10.68, etc) and is not matching timesheet hours?
We are using the "Hours of Work Done per Day" tracking method with Lock Down
Defaults and Managed Periods enabled.
For example,
I have a resource who has work assigned on a task, but no time entered in
her timesheet for that task. But, somehow, time was entered into the Actual
Work field in Project Professional.
Other times, when I open a project and there is time remaining in a task,
for some reason the actual work field gets recalculated so that the Actual
Work field is all screwy... We have people sync to actuals and save,
everything is ok, but when they reopen the project, the hours are wrong
again. Is this a symptom of us not republishing all information? I just got
on this project and I'm trying to figure out all these problems they're
experiencing... any help? Dale, Gary?
Steve
inhuman hours (.28, 3.87, 10.68, etc) and is not matching timesheet hours?
We are using the "Hours of Work Done per Day" tracking method with Lock Down
Defaults and Managed Periods enabled.
For example,
I have a resource who has work assigned on a task, but no time entered in
her timesheet for that task. But, somehow, time was entered into the Actual
Work field in Project Professional.
Other times, when I open a project and there is time remaining in a task,
for some reason the actual work field gets recalculated so that the Actual
Work field is all screwy... We have people sync to actuals and save,
everything is ok, but when they reopen the project, the hours are wrong
again. Is this a symptom of us not republishing all information? I just got
on this project and I'm trying to figure out all these problems they're
experiencing... any help? Dale, Gary?
Steve