Tim @ NARA
I accidentally approved actual hours submitted against a summary task
(uncertain how or why a user is able to submit hours to a summary task). I
attempted to zero out the hours using "Adjust Actuals" in PWA, but the result
I expected (an adjustment of actual hours in the summary task to 0) back in
Project Professional didn't occur. Project Professional actually increased
the hours (from 47 submitted to 124.23).
My coworker suggested adjusting the hours in Project Professional (zero'ing
out the actual hours in the Task Form view), but the consultant who
implemented Project Server for us said not to adjust actual hours in this
manner (instead use PWA which I attempted).
Any recommendations?
(uncertain how or why a user is able to submit hours to a summary task). I
attempted to zero out the hours using "Adjust Actuals" in PWA, but the result
I expected (an adjustment of actual hours in the summary task to 0) back in
Project Professional didn't occur. Project Professional actually increased
the hours (from 47 submitted to 124.23).
My coworker suggested adjusting the hours in Project Professional (zero'ing
out the actual hours in the Task Form view), but the consultant who
implemented Project Server for us said not to adjust actual hours in this
manner (instead use PWA which I attempted).
Any recommendations?