T
tshad
How do you tell the program to run for 3 months?
The problem is that if I say start on 01/01/09, it will go to 03/25/09 when
I really want it to go to 03/31/09.
I then need to have the lag date 1 month so it starts at 02/01/09, but
instead when I enter 1mo it goes to 01/29/09.
This project is going to start on the 1st day of the month and all the tasks
are going to run for even months (months 2-4 or 5-9).
I want to be able to change the start date to 02/01/09 and have it calculate
the dates correctly.
Is there a way to do this?
Also, how can can I have the milestone start on the next day? If I have a
task that stops on 12/31/09 and then a milestone which says "Phase 2 Year
2" - It shows the milestone on 12/31/09 instead of 01/01/10.
Thanks,
Tom
The problem is that if I say start on 01/01/09, it will go to 03/25/09 when
I really want it to go to 03/31/09.
I then need to have the lag date 1 month so it starts at 02/01/09, but
instead when I enter 1mo it goes to 01/29/09.
This project is going to start on the 1st day of the month and all the tasks
are going to run for even months (months 2-4 or 5-9).
I want to be able to change the start date to 02/01/09 and have it calculate
the dates correctly.
Is there a way to do this?
Also, how can can I have the milestone start on the next day? If I have a
task that stops on 12/31/09 and then a milestone which says "Phase 2 Year
2" - It shows the milestone on 12/31/09 instead of 01/01/10.
Thanks,
Tom