Actual Overtime Work

J

Jesse

In Project 2002 and PWA, Actual Work INCLUDES Actual Overtime Work, whereas
in Project Central Actual Work did NOT include Actual Overtime Work.
This allowed me to show overtime hours or not. Now, I'm stuck with them
showing up all the time - either explicitly broken out if "show overtime
work" is checked or implicitly included in actual work if it is not checked.

I am looking for suggestions to strip out the overtime work, since I cannot
do it like I used to in Project Central.

TIA,
Jesse
 
D

Dale Howard

Jesse --

By definition, the Work field is calculated as follows:

Work = Regular Work + Overtime Work + Remaining Work

Regular Work is obviously non-overtime work. All three of these fields can
be seen in either the Task Usage or Resource Usage views as rows in the
timephased grid and as columns in the Task Sheet or Resource Sheet. You
don't have to strip out Overtime Work. Instead, apply the Regular Work
column or row and you're in business. Hope this helps.

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
Top