F
Fred Jones
Hi,
We're running Project Web access and project. I've set up the timesheets so
that team members can enter Actual Start, Actual Work, Work Remaining and
Actual Finish. The original tasks in Project were set up with multiple
resources per task and each resource having around 15% units. It appears
that when the resources update their task information the units change from
15% to 100%. The hours seem to stay as entered except for people that enter
an Actual Finish that is later than the Finish date. In this case the
task/resource hours are greatly inflated and inaccurate.
What am I doing wrong? Is it incorrect to use Actual Start/Finish along with
hours tracking? Do I need to use just the Actual Start with the hours
worked?
What I was trying to achieve was a more accurate accounting of the actual
hours they worked along with a more accurate view of the percent time they
devoted to that task. My thinking was that the actual hours, combined with
the actual finish/start, might present a more accurate units calculation.
Instead, all of the units go to 100%, which is inaccurate.
Thanks for any insight or ideas...
We're running Project Web access and project. I've set up the timesheets so
that team members can enter Actual Start, Actual Work, Work Remaining and
Actual Finish. The original tasks in Project were set up with multiple
resources per task and each resource having around 15% units. It appears
that when the resources update their task information the units change from
15% to 100%. The hours seem to stay as entered except for people that enter
an Actual Finish that is later than the Finish date. In this case the
task/resource hours are greatly inflated and inaccurate.
What am I doing wrong? Is it incorrect to use Actual Start/Finish along with
hours tracking? Do I need to use just the Actual Start with the hours
worked?
What I was trying to achieve was a more accurate accounting of the actual
hours they worked along with a more accurate view of the percent time they
devoted to that task. My thinking was that the actual hours, combined with
the actual finish/start, might present a more accurate units calculation.
Instead, all of the units go to 100%, which is inaccurate.
Thanks for any insight or ideas...