J
Jeff
I'm using Project 2003 and new to the product. I'd like to know if it's
possible that after defining a Task with start and finish times, to input the
actual time that elapsed to complete the task. So for example, There's task A
that was scheduled to be completed in 90 days. But it actually took 120 days.
Can project track that sort of thing to report on, see in the various pane
windows so forth and so on. To see and report on project not following the
"original" plan, over runs with respect to time etc.
possible that after defining a Task with start and finish times, to input the
actual time that elapsed to complete the task. So for example, There's task A
that was scheduled to be completed in 90 days. But it actually took 120 days.
Can project track that sort of thing to report on, see in the various pane
windows so forth and so on. To see and report on project not following the
"original" plan, over runs with respect to time etc.