T
Tomi
HI,
Used SW: MS Project 2002 & MS Project Server
I have a case where I'm not sure is it feature or bug in
Project. Case is
1. There is task published for the developer via server.
2. Schedule work hours are eg 5hour per day.
3. Developer adds actual, real hours and update data into
server. It could be like
day1 day2 day3
WORK: 5 5 5
Act. 3 4
4. I update my plan and if I look added hours again it
looks like
day1 day2 day3
WORK: 3 4 5
Act. 3 4
All work hours are same like actuals?
We use those data in server to find out how our planned
hours meets actuals. So is this bug or feature? If this is
a feature what we should use if we like to study planned
vs actual work? Note! I do not use baselines.
-Tomi
Used SW: MS Project 2002 & MS Project Server
I have a case where I'm not sure is it feature or bug in
Project. Case is
1. There is task published for the developer via server.
2. Schedule work hours are eg 5hour per day.
3. Developer adds actual, real hours and update data into
server. It could be like
day1 day2 day3
WORK: 5 5 5
Act. 3 4
4. I update my plan and if I look added hours again it
looks like
day1 day2 day3
WORK: 3 4 5
Act. 3 4
All work hours are same like actuals?
We use those data in server to find out how our planned
hours meets actuals. So is this bug or feature? If this is
a feature what we should use if we like to study planned
vs actual work? Note! I do not use baselines.
-Tomi