M
MJ
Hi, recently we've upgrated from MS Project 2003 to 2007. One of my users
has a complain about entering hours.
In 2003, when there is a task that was non-project related (fixed work), she
planned flat 2 hours a week thru. out the year for 2 differnt resources. In
reality, that 2 resources didn't have any actual for week 4 & 5, in order to
keep the future work balaced, and not changed the finish day, what she did
was enter "0" in the work cell for that 3 weeks, everything remained the same
in the future weeks. However, in 2007 version, it didn't act the same way as
2003. It actually changed the start date, and moved the future hours to week
2 & 3. At the mean time, it also moved the other resource's future hours.
Anyone has any explanations or any suggustions to handle this issue?
Thanks in advance!
has a complain about entering hours.
In 2003, when there is a task that was non-project related (fixed work), she
planned flat 2 hours a week thru. out the year for 2 differnt resources. In
reality, that 2 resources didn't have any actual for week 4 & 5, in order to
keep the future work balaced, and not changed the finish day, what she did
was enter "0" in the work cell for that 3 weeks, everything remained the same
in the future weeks. However, in 2007 version, it didn't act the same way as
2003. It actually changed the start date, and moved the future hours to week
2 & 3. At the mean time, it also moved the other resource's future hours.
Anyone has any explanations or any suggustions to handle this issue?
Thanks in advance!