J
Jim Puls
I have a task which takes 2 hours to complete and is to be done over a
period (duration) of 5 days. After a day, I set the actual work for
the task to 1 hour. A couple of days later, the second hour of work
has been done and the task is complete, so I set the percent complete
to 100%. Actual work is immediately set to 40 hours, 5 days times 8
hours per day. How should I set up the task so that the duration is 5
days, but 100% of the work is 2 hours?
Thanks, Jim
period (duration) of 5 days. After a day, I set the actual work for
the task to 1 hour. A couple of days later, the second hour of work
has been done and the task is complete, so I set the percent complete
to 100%. Actual work is immediately set to 40 hours, 5 days times 8
hours per day. How should I set up the task so that the duration is 5
days, but 100% of the work is 2 hours?
Thanks, Jim