Actual work change after publish to the 2007 server

X

xho

Hello,
Here's a problem we recently met :
We've migrate ProjectServer 2003 planning to 2007 true MPP file :
Save as file and the save file to the server.
Those plannings have actual (protected) work.
When saving and publishing the 2007 server, some actual work start to
change :
for exemple : 2h monday became 0,03h sunday and the rest monday.

Same resource name and capacity
Same calendar
Same rules to manage time and work.

Any help ?
Thanks
Xavier
 
P

ProjmanZA

Xavier ,

Are the latetest updates installed on the Project 2007 Server ? If i
am not wrong there was a know bug with the actual work.
 
X

xhovasse

Hello,
Thanks for your help.
The most recent update is from August.
The fix you mention is more recent ?

Xavier
 