G
Gary Johnson
The main issue we are seeing is 'actual work' changing historically.
Snapshots of the same task in March 03 have been taken on different dates
this year 26 Jan and 3 Feb.
I am running a split view with Task Usage in the upper view and task details
in the lower view.
In the Task details form (lower window) both snapshots show the actual work
as 20hrs and the task complete. There is one resource assigned to the task.
In the upper section the hours booked are different the first one (26th Jan)
showing 13.75 hours and the corresponding cost at £50/hr £687.5, the other
one taken at 3 Feb showing 20hrs and £1000.
Why would this be ?
To begin with there is a simple anomoly in the first case - why would the
assignment show 13.75 h actual work in the upper view, but shows 20h for the
assignment in the task details form - that in itself just doesn't make
sense.
This appears to be something happening within the software. No one has had
any reason to tamper with this task as it is so old. On the same screen shot
it shows conflicting information.
I can send a screenshot through if necessary.
Appreciate it if anyone has any ideas .....
Thanks
Gary
Snapshots of the same task in March 03 have been taken on different dates
this year 26 Jan and 3 Feb.
I am running a split view with Task Usage in the upper view and task details
in the lower view.
In the Task details form (lower window) both snapshots show the actual work
as 20hrs and the task complete. There is one resource assigned to the task.
In the upper section the hours booked are different the first one (26th Jan)
showing 13.75 hours and the corresponding cost at £50/hr £687.5, the other
one taken at 3 Feb showing 20hrs and £1000.
Why would this be ?
To begin with there is a simple anomoly in the first case - why would the
assignment show 13.75 h actual work in the upper view, but shows 20h for the
assignment in the task details form - that in itself just doesn't make
sense.
This appears to be something happening within the software. No one has had
any reason to tamper with this task as it is so old. On the same screen shot
it shows conflicting information.
I can send a screenshot through if necessary.
Appreciate it if anyone has any ideas .....
Thanks
Gary