Susan
Our resources go into server 2002 to log time to a task: Lets say they log 30
hours on a task that was esimated to take 40 and they are done. When the
project manager goes back into the plan and marks the task 100% complete the
actual hours changes to 40. Which is incorrect. Why does it do that?