Hi All,

I am using EPM 2003 in my organization. I am analyzing the resource
information in the portfolio analyzer. I am building a view with resource
name, actual work by day reported by the resource. Although the
resource has keyed in the actual work, it is showing 0 in the Portfolio
report. The cube has been built successfully. Any help?

Regards
Sneha
 
D

Dale Howard [MVP]

Sneha --

Has the PM actually accepted the resource's task progress and then published
the latest schedule changes? Remeber that only published information
appears in the OLAP cube in Project Server 2003. Let us know.
 