B
Brian
We have just reconfigured MS Project Server 2003 in one area of my
organization. Resources were entering actuals per week and non-managed
periods. They are now entering actuals per day and using managed periods.
We reimported the plans onto the server once it was reconfigured. Now some
of the actual work extends into the future for those tasks that have been
marked complete. Other than using the Adjust Actuals view, is there any
other way to correct this? Thank you.