Actual Work has different value in different panes

J

Jørgen Strand

Hi,

i've got an issue with a stand alone project professional
2002. Currently a work plan exists with actual work data
in it. When i go to the resource usage view (or similar
views) i have a disrepancy between the actual work numbers
viewed in the left pane and the actual work numbers in the
right pane for only one resource.

I have only this plan open, so there are no other data to
interfere. Furthermore, there are no master-sub
relationship or resource pools that can interfere.

The plan has been baseline, but i tried to clear the
baseline to see if it could have an impact. - NONE.

This is really boggering me, since we're currently on the
track to roll out a complete project + server solution to
a thousand users. There are contractual and auditing
requirements which really cannot allow these kinds of
issues.

We're now currently trying to find out what a resource has
been actually working six months ago, which is close to
impossible.

Any hints would be nice...

Regards,

Jørgen Strand
 
M

Mike Glen

Hi Jørgen ,

Welcome to this Microsoft Project newsgroup :)

The figures should be the same. Have you any resources assigned to Summary
tasks?

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP

And yes, I've tried to recalculate the plan manually.
 