Jørgen Strand
Hi,
i've got an issue with a stand alone project professional
2002. Currently a work plan exists with actual work data
in it. When i go to the resource usage view (or similar
views) i have a disrepancy between the actual work numbers
viewed in the left pane and the actual work numbers in the
right pane for only one resource.
I have only this plan open, so there are no other data to
interfere. Furthermore, there are no master-sub
relationship or resource pools that can interfere.
The plan has been baseline, but i tried to clear the
baseline to see if it could have an impact. - NONE.
This is really boggering me, since we're currently on the
track to roll out a complete project + server solution to
a thousand users. There are contractual and auditing
requirements which really cannot allow these kinds of
issues.
We're now currently trying to find out what a resource has
been actually working six months ago, which is close to
impossible.
Any hints would be nice...
Regards,
Jørgen Strand
i've got an issue with a stand alone project professional
2002. Currently a work plan exists with actual work data
in it. When i go to the resource usage view (or similar
views) i have a disrepancy between the actual work numbers
viewed in the left pane and the actual work numbers in the
right pane for only one resource.
I have only this plan open, so there are no other data to
interfere. Furthermore, there are no master-sub
relationship or resource pools that can interfere.
The plan has been baseline, but i tried to clear the
baseline to see if it could have an impact. - NONE.
This is really boggering me, since we're currently on the
track to roll out a complete project + server solution to
a thousand users. There are contractual and auditing
requirements which really cannot allow these kinds of
issues.
We're now currently trying to find out what a resource has
been actually working six months ago, which is close to
impossible.
Any hints would be nice...
Regards,
Jørgen Strand