The Actual Work hours for some of my resources are not the
same as Actual Work hours shown in their timesheet in PWA,
nor the Actual Work hours shown in the Task Usage View
within the projects in MS Project 2002 Professional. For
example, one of my resources is showing 232 hours for one
day and I'm not able to find any odd figures under any of
his tasks.
All tasks are set to Fixed Duration, Not Effort Driven, if
that helps. This just started happening, and we're
following the same process as before. Has anyone else
experienced this?
Thanks,
DJ
same as Actual Work hours shown in their timesheet in PWA,
nor the Actual Work hours shown in the Task Usage View
within the projects in MS Project 2002 Professional. For
example, one of my resources is showing 232 hours for one
day and I'm not able to find any odd figures under any of
his tasks.
All tasks are set to Fixed Duration, Not Effort Driven, if
that helps. This just started happening, and we're
following the same process as before. Has anyone else
experienced this?
Thanks,
DJ