Actual work in Project Center

  • Thread starter Jose M. Dominguez
  • Start date
J

Jose M. Dominguez

Hello :

I'm working with project center views in project web
access 2003. I have managed to visualize work, start and
finish fields but I don't know why actual work doesn't
appear. It is configured in the same way.

In the projects views everything is fine though.

Does anybody know why?

Thanks
Jose
 
D

Dale Howard [MVP]

Jose --

Are you actually publishing the projects using Collaborate - Publish - All
Information?
 
G

Guest

Hello Dale:

Yes I am publishing all the information.
The curious thing is that I can see actual work on
Projects views but not on project center views.

I have created views in the admin section manage views,
and the other fields are displayed correctly.

Jose
 
A

Atle Esperum

Hello,

I'm having the same problem with actual work in project center views. When I
publish all information in MS Project 3 errors occurs in the Event log at
the server:

Description:
Component: PjMsgHlr
File: C:\Office\dev\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp
Line: 570
Error Number: 0x80004005
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

Description:
Component: PjMsgHlr
File: C:\Office\dev\project\WebClient\source\server\pjmsghlr\dbupddata.cpp
Line: 1624
Error Number: 0x80020005
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

Description:
Component: PjMsgHlr
File: C:\Office\dev\project\WebClient\source\server\pjmsghlr\dbupddata.cpp
Line: 2076
Error Number: 0x80004005
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>


Thanks
Atle Esperum
 
A

AVC

Hello,

I have the same problem only with one Plan, the fields are actual work, start date and finish date in Project Center Views. The other plan is right in the same Project Server.
Is there a hotfix?
 
Top