M
Michal Pleban
Hello!
Here's another newbie question about MS Project Server 2002. I set up
the Server ans MSProj Pro correctly. I use Web Access for resources to
report their completion opf the tasks assigned. When one logs into the
Web Access and clicks on Tasks, he can report the percent of completion
of his tasks and time remaining to complete.
However, when I click on a "Time shett view" instead of "Gantt chart", i
see another table showing "Actual work" for every week. In this table,
all columns are blank or "0h", even when Actual work in the left part of
the table is nonzero for a given task. The fields in this table are
grayed out so I can't enter values there. How to display correct values
in this table?
Thanks,
Michau.
Here's another newbie question about MS Project Server 2002. I set up
the Server ans MSProj Pro correctly. I use Web Access for resources to
report their completion opf the tasks assigned. When one logs into the
Web Access and clicks on Tasks, he can report the percent of completion
of his tasks and time remaining to complete.
However, when I click on a "Time shett view" instead of "Gantt chart", i
see another table showing "Actual work" for every week. In this table,
all columns are blank or "0h", even when Actual work in the left part of
the table is nonzero for a given task. The fields in this table are
grayed out so I can't enter values there. How to display correct values
in this table?
Thanks,
Michau.