S
Scott McClure
Background: Our tasks are effort-driven and fixed units. Constraints are
avoided. Our resources are groups of skills with 100% = 1 person. The
calendar for the resource shows a 10 1/2 hour day with a 1/2 hour lunch. We
are running PS and MSP2002.
We enter our actual work centrally via a slightly modified Task Usage screen
in Project Pro.
Problem: Sometimes, for reasons we don't understand, when a time, say 1
hour, is entered for a task, the software breaks that time up and moves some
of it to the next day. In this case the day we are entering takes .8 and
the next day (the future) gets .2.
We had thought this might be because the resource was tapped out -- out of
available hours for the day. In this case the resource has 6 units
available or 60 hours. When the 1 hours was split into today and tomorrow,
the result of adding that 1 hour to the resource would have resulted in a
total reported labor of 32 hours. This sort of blows theory one.
Now, the previous day 69 hours were reported. Question: does this affect
how actual hours are accepted for subsequent days? If so, how? I know that
MSP thinks minute-to-minute but even if the entire 9 hours were moved into
today this still would have only resulted in 41 (of 60 available) hours
used.
This is most frustrating to our data-entry person and prevents us from using
a macro to automatically load the actual hours from our work order system
because we don't trust what MSP will do with it.
Is there any way to resolve this???
TIA,
Scott McClure
avoided. Our resources are groups of skills with 100% = 1 person. The
calendar for the resource shows a 10 1/2 hour day with a 1/2 hour lunch. We
are running PS and MSP2002.
We enter our actual work centrally via a slightly modified Task Usage screen
in Project Pro.
Problem: Sometimes, for reasons we don't understand, when a time, say 1
hour, is entered for a task, the software breaks that time up and moves some
of it to the next day. In this case the day we are entering takes .8 and
the next day (the future) gets .2.
We had thought this might be because the resource was tapped out -- out of
available hours for the day. In this case the resource has 6 units
available or 60 hours. When the 1 hours was split into today and tomorrow,
the result of adding that 1 hour to the resource would have resulted in a
total reported labor of 32 hours. This sort of blows theory one.
Now, the previous day 69 hours were reported. Question: does this affect
how actual hours are accepted for subsequent days? If so, how? I know that
MSP thinks minute-to-minute but even if the entire 9 hours were moved into
today this still would have only resulted in 41 (of 60 available) hours
used.
This is most frustrating to our data-entry person and prevents us from using
a macro to automatically load the actual hours from our work order system
because we don't trust what MSP will do with it.
Is there any way to resolve this???
TIA,
Scott McClure