Actual Work: Off-line vs Project Server 2003

S

Stefan van Aalst

Hi

We experience the following:
When on Project Server In Resource Usage we see:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: only work (not actual work, not actual cost, etc)

When I do a shared resource thing off-line, I see in Resource Usage:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: work, actual work, etc

Is there a setting not okay in the server or is something else the reason
why for non-opened projects Actual Work is empty in MS-project when connected
to project server?

I would expect, more than in the off-line thing, to see all actuals even
when the project is not opened.

Much obliged

Stefanb
 