Actual Work Question

R

RandyK

Is there any way that Actual Work Protected (AWP) can appear in Project Pro
for a specific task - but those hours not visible in Adjust Actuals (or
Resource Assignment View) in PWA for the same task?
 
D

Dale Howard [MVP]

RandyK --

I'm afraid not. If you have the Adjust Actuals permission, Project Server
exposes the Actual Work Projected data to you. Sorry.
 