Colin Anderson
We are experiencing some problems when team members use
Project Web Access to report their actual work.
An example: Hours typed in for one week also appear - seen
from the Project Pro 2002 client - in the previous week.
These double hours are not visible in the team member's
Task Page in Web Access.
Similarly, other hours typed in for a specific date, seem
to turn up at another date, when viewed in the client
program.
The persons involved claim that they have NOT typed Actual
Work in via the client. We have already seen that these
hours are not visible in the web interface.
We have investigated the Web-Work table to see if we could
find some pattern in the errors but to no avail. We are
now beginning to think, that there may be a bug in the
product(s).
Has anyone else experienced similar problems?
Project Web Access to report their actual work.
An example: Hours typed in for one week also appear - seen
from the Project Pro 2002 client - in the previous week.
These double hours are not visible in the team member's
Task Page in Web Access.
Similarly, other hours typed in for a specific date, seem
to turn up at another date, when viewed in the client
program.
The persons involved claim that they have NOT typed Actual
Work in via the client. We have already seen that these
hours are not visible in the web interface.
We have investigated the Web-Work table to see if we could
find some pattern in the errors but to no avail. We are
now beginning to think, that there may be a bug in the
product(s).
Has anyone else experienced similar problems?