T
Teresa S
Using Project Server 2007, we set in the task settings and display to use
actual work done and work remaining, force the PMs to use. It appears that
this only applies to project tasks and not to tasks in proposals and
activities. Is that correct or did we miss something? We would like
resources to always report actual work done and work remaining on projects
AND activities.
TIA
Teresa
actual work done and work remaining, force the PMs to use. It appears that
this only applies to project tasks and not to tasks in proposals and
activities. Is that correct or did we miss something? We would like
resources to always report actual work done and work remaining on projects
AND activities.
TIA
Teresa