While using the Timesheets on the Project Server to update
the actual on MS Project. I am facing a problem, if I have
2 or more resources assigned to a task. If one resources
updates the actuals & send PM fo approvals. The % complete
on the task changes- it also updates the actual work
entries on the other resources who have not yet sent their
actuals for approval.
How can this be solved as it will show incorrect entries
on the report? Is this the way the Timesheets are supposed
to work? Any urgent help would be appreciated?
Regards,
David.
the actual on MS Project. I am facing a problem, if I have
2 or more resources assigned to a task. If one resources
updates the actuals & send PM fo approvals. The % complete
on the task changes- it also updates the actual work
entries on the other resources who have not yet sent their
actuals for approval.
How can this be solved as it will show incorrect entries
on the report? Is this the way the Timesheets are supposed
to work? Any urgent help would be appreciated?
Regards,
David.