Actual work vs Percent Complete

J

JD

I have a task that I estimated at 25 hours to compete but actually took 20 -
now it only less than 100% -

How can I configure it to show 100% complete even though it took less hours
than estimated?

Thanks.
 
D

Dale Howard [MVP]

JD --

Adjust the Remaining Work value for the task to 0 hours. This will mark the
task as 100% complete automatically. Hope this helps.
 