O
Olevangjensen
Hello,
I am administrating a rather large project i Project Server 2002. Now I have
discovered that when the ressources in the project make time reportings, then
when looking at Actual Work, then the time is correct, but when looking at
Work then sometimes it is the same as Actual Work, but othertimes their just
stands a long row of similar times - always strange decimal times, e.g. 1,32
long into the future. I cannot find out what is wrong?
I am administrating a rather large project i Project Server 2002. Now I have
discovered that when the ressources in the project make time reportings, then
when looking at Actual Work, then the time is correct, but when looking at
Work then sometimes it is the same as Actual Work, but othertimes their just
stands a long row of similar times - always strange decimal times, e.g. 1,32
long into the future. I cannot find out what is wrong?