D
dee
Dear All,
I have done this:
1. Manager have published project and task was displayed in my task
2. Updated my timesheet (actual work), saved and submitted, then manager
give approval to my time sheet
3. I see the progress that have been updated in my task, and I import my task
But, the actual work is not update in ms project file. What should I do?
And how did I set to display timesheet view with column : work, % work
acomplete, actual work. Now I only can display start, finish, progress column
in timesheet view
Thx all
Dee
I have done this:
1. Manager have published project and task was displayed in my task
2. Updated my timesheet (actual work), saved and submitted, then manager
give approval to my time sheet
3. I see the progress that have been updated in my task, and I import my task
But, the actual work is not update in ms project file. What should I do?
And how did I set to display timesheet view with column : work, % work
acomplete, actual work. Now I only can display start, finish, progress column
in timesheet view
Thx all
Dee