S
Steve
I have my project set up to track actual work on a daily
basis. I have a task set up that requires 4 hours of work
and 2 resources assigned to it at 100% each. If one of
those resources enters actual hours against the task that
totals 4 hours and then I set the percent completion to
100, the project shows more than 4 actual hours. If I
look at the individual resource information for the task,
it shows that both of the resources have actuals against
it even though only the 1 entered actuals. Am I doing
something fundamentally wrong here in the configuration?
Why would the actuals ever show more than what was really
entered?
basis. I have a task set up that requires 4 hours of work
and 2 resources assigned to it at 100% each. If one of
those resources enters actual hours against the task that
totals 4 hours and then I set the percent completion to
100, the project shows more than 4 actual hours. If I
look at the individual resource information for the task,
it shows that both of the resources have actuals against
it even though only the 1 entered actuals. Am I doing
something fundamentally wrong here in the configuration?
Why would the actuals ever show more than what was really
entered?