M
Muddypaws
Not sure if this is possible, being a newby to MS Project, but......
I have created a resource pool and detailed the availability of each
person. What I am trying to do, and struggling with it:
1. Someone has created a task and said it will take 5 days, however
the person allocated completed it in 2 days. This is where I get
confused because I leave the days as is, but go to the Tasj Sheet and
select Work to view the Work column and change it to say 2 days. But
then the whole dates change completely. I want it to show say 1st Jan
to 5th Jan which is what was estimated, but it only took from 1st Jan
to 3rd Jan and the person was avilable for that task for 2% of his/her
time? So I save XXXX number of hours etc
2. In the resource pool which is linked to my other 9 projects, when
the allocate a person to a task, can MS Project notify them
automatically to say that they cannot use this person as they are
alocated elsewhere?
3. When a task is due or overdue how can MS Project notify the user?
Thanks
I have created a resource pool and detailed the availability of each
person. What I am trying to do, and struggling with it:
1. Someone has created a task and said it will take 5 days, however
the person allocated completed it in 2 days. This is where I get
confused because I leave the days as is, but go to the Tasj Sheet and
select Work to view the Work column and change it to say 2 days. But
then the whole dates change completely. I want it to show say 1st Jan
to 5th Jan which is what was estimated, but it only took from 1st Jan
to 3rd Jan and the person was avilable for that task for 2% of his/her
time? So I save XXXX number of hours etc
2. In the resource pool which is linked to my other 9 projects, when
the allocate a person to a task, can MS Project notify them
automatically to say that they cannot use this person as they are
alocated elsewhere?
3. When a task is due or overdue how can MS Project notify the user?
Thanks