J
James
Hi,
We are running Project Server 2002 - but we have a problem whereby actuals
already entered against tasks are changing.
We are using fixed work tasks (effort driven) and have several resources
assigned to the tasks.
There doesn't seem to be any logical pattern to it. All I can say is that
mpp versions of our project that WERE the same don't match the current
actuals in our published version of the plan. Even for tasks that go back
to the beginning of last year.
Has anyone else seen or experienced this problem ? And are there any
workarounds/fixes for this ?
Does anyone know how it is that actuals can change ? By definition I would
have thought that ince entered actuals should never change !! But they are
!
Thanks
James
We are running Project Server 2002 - but we have a problem whereby actuals
already entered against tasks are changing.
We are using fixed work tasks (effort driven) and have several resources
assigned to the tasks.
There doesn't seem to be any logical pattern to it. All I can say is that
mpp versions of our project that WERE the same don't match the current
actuals in our published version of the plan. Even for tasks that go back
to the beginning of last year.
Has anyone else seen or experienced this problem ? And are there any
workarounds/fixes for this ?
Does anyone know how it is that actuals can change ? By definition I would
have thought that ince entered actuals should never change !! But they are
!
Thanks
James