M
Maria Pabon
In Project Professional 2002
I try to capture hours on a daily basis and enter them on the actual work field. If I update the task percentage (for instance), it will change the actuals. This does not make sense, the fact that I think the %complete is different than the calculated does not change the actual value, it changes the estimated work, the duration, etc but not the actuals. (switching the calculation switch about updating resource status when task status changes seems to help but there is no reason to change actual time reported
In another case, I added a new resource to a task and this resource started with some actual hours already. This problems do not allow me to use project to double check time reporting and require me to have additional spreadsheets keeping track of resource time
I try to capture hours on a daily basis and enter them on the actual work field. If I update the task percentage (for instance), it will change the actuals. This does not make sense, the fact that I think the %complete is different than the calculated does not change the actual value, it changes the estimated work, the duration, etc but not the actuals. (switching the calculation switch about updating resource status when task status changes seems to help but there is no reason to change actual time reported
In another case, I added a new resource to a task and this resource started with some actual hours already. This problems do not allow me to use project to double check time reporting and require me to have additional spreadsheets keeping track of resource time