K
Kevin
We are having a problem on occasion with actual hours
disappearing from projects for past weeks. Most of my
Project Managers using Project Server say this has
happened to them more than once, but they usually do not
notice it until it's too late to pin it down. One
particular instance occurred within the last several
weeks. The project leader says it occurred on at least 3
tasks for the same resource. Updates from other resources
to the same project the same week all worked fine.
Any ideas would be helpful
disappearing from projects for past weeks. Most of my
Project Managers using Project Server say this has
happened to them more than once, but they usually do not
notice it until it's too late to pin it down. One
particular instance occurred within the last several
weeks. The project leader says it occurred on at least 3
tasks for the same resource. Updates from other resources
to the same project the same week all worked fine.
Any ideas would be helpful