Actuals do not match Actual Work Protected

  • Thread starter The Great Caper
  • Start date
T

The Great Caper

I have just published a plan that has approx. 30% of all work completed. When
I receive a task update from a resource, the update only accepts the new
hours and removes the original hours that were in the plan before publishing.
How do I protect these original actuals?
We are not using managed time periods and our progress reporting method is
Hours of work done per day or per week.

Any ideas?

Thanks

GC!
 
D

Dale Howard [MVP]

GC --

Did you manually enter the 30% of the work that was done previously? If so,
you needed to click Collaborate - Publish - Republish Assignments, select
the "Ovewrite actual work entered by resources" option, and click OK to
"push" the manually-entered actuals to each resource's timesheet in PWA.
Hope this helps.
 
T

The Great Caper

Yes it does help, however I do have some protected actuals, as I have
accepted hours for one reporting period through Project Server - will I loose
those hours?

Thanks,

GC
 
D

Dale Howard [MVP]

GC --

Projected actuals are only used with the Managed Time Periods option in
Project Server. You should not lose those numbers, however. Hope this
helps.
 
T

The Great Caper

Hi Dale,

I have done as you suggested and republished all assignments - overwrite
actual work entered by resources. When I go to PWA to update a resources
actuals, I loose all of the historical data (actuals) that I have entered
into the plan so far, in some cases that is several hundred hours.
Any ideas?

Thanks.
 
T

The Great Caper

Hi Dale,

I have done as you suggested and republished all assignments - overwrite
actual work entered by resources. When I go to PWA to update a resources
actuals, I loose all of the historical data (actuals) that I have entered
into the plan so far, in some cases that is several hundred hours.
Any ideas?

Thanks.
 