T
The Great Caper
I have just published a plan that has approx. 30% of all work completed. When
I receive a task update from a resource, the update only accepts the new
hours and removes the original hours that were in the plan before publishing.
How do I protect these original actuals?
We are not using managed time periods and our progress reporting method is
Hours of work done per day or per week.
Any ideas?
Thanks
GC!
I receive a task update from a resource, the update only accepts the new
hours and removes the original hours that were in the plan before publishing.
How do I protect these original actuals?
We are not using managed time periods and our progress reporting method is
Hours of work done per day or per week.
Any ideas?
Thanks
GC!