U
uffeh
We recently completed the implementation of Project Server 2007, and had all
our resources input their timesheets from the beginning of this year up to
the present. The problem that I have is that when I look at the OLAP cube
and display the Actual Cost over time, I get values that do not correspond
to the actual timesheet entries, i.e. we have actual costs for December 2006
even though no time was recorded for that month. When I look at the tasks
corresponding to those actual costs, I can see that Project has moved the
start dates in some cases back to December 2006. This is of course annoying
in itself, and would presumably result only in the cube showing planned cost
for December 2006 - and not actual costs. Aren't Actual Costs supposed to be
a direct computation of time reported on the timesheets times billing rates?
Has anyone else experienced this?
our resources input their timesheets from the beginning of this year up to
the present. The problem that I have is that when I look at the OLAP cube
and display the Actual Cost over time, I get values that do not correspond
to the actual timesheet entries, i.e. we have actual costs for December 2006
even though no time was recorded for that month. When I look at the tasks
corresponding to those actual costs, I can see that Project has moved the
start dates in some cases back to December 2006. This is of course annoying
in itself, and would presumably result only in the cube showing planned cost
for December 2006 - and not actual costs. Aren't Actual Costs supposed to be
a direct computation of time reported on the timesheets times billing rates?
Has anyone else experienced this?