D
D3Consulting
I had to remove some hours off a task and add the same hours to
another task (we already closed our timesheet period). After I moved
the hours I updated the hours (approved them) then went into my plan
and re-sync up with actuals, republished but yet the Actual Hours are
still in the task that I removed the hours from.
What can I do to fix this?
Thanks,
David
another task (we already closed our timesheet period). After I moved
the hours I updated the hours (approved them) then went into my plan
and re-sync up with actuals, republished but yet the Actual Hours are
still in the task that I removed the hours from.
What can I do to fix this?
Thanks,
David