E
Erkki
Hi.
In my case some of the projects are underway and some tasks are completed.
These are marked 100% complete in MSP (and the actuals for remaining tasks
are keyed in WA later on) . When I publish these complete tasks/assignments
to WA their actual work is shown in project and task views but is not present
in resource assignments. The remedy is to republish and check Overwrite
actuals.
My question : Is this the only and correct procedure ?
Thank you!
Erkki
In my case some of the projects are underway and some tasks are completed.
These are marked 100% complete in MSP (and the actuals for remaining tasks
are keyed in WA later on) . When I publish these complete tasks/assignments
to WA their actual work is shown in project and task views but is not present
in resource assignments. The remedy is to republish and check Overwrite
actuals.
My question : Is this the only and correct procedure ?
Thank you!
Erkki