For some resource actuals submitted by the resources do not show up in
the task grid on the "View task changes submitted by resource" page.
For a given project some resources will show all actuals submitted and
for some the actuals cell is blank. But when the I go ahead and
accept the changes with the missing actuals the actuals submitted do
show up on the project plan. The behavior seems random because not
all projects are affected and I can not reproduced this error in
development. This article
http://www.kbalertz.com/Feedback_834717.aspx shows a similar problem
that MS released a hotfix for. Unfortunately the hot fix requires a
client side install and server install. We have many desktops and I
don't want to patch every desktop if at all possible. Has anyone
experienced this problem?
Hip
the task grid on the "View task changes submitted by resource" page.
For a given project some resources will show all actuals submitted and
for some the actuals cell is blank. But when the I go ahead and
accept the changes with the missing actuals the actuals submitted do
show up on the project plan. The behavior seems random because not
all projects are affected and I can not reproduced this error in
development. This article
http://www.kbalertz.com/Feedback_834717.aspx shows a similar problem
that MS released a hotfix for. Unfortunately the hot fix requires a
client side install and server install. We have many desktops and I
don't want to patch every desktop if at all possible. Has anyone
experienced this problem?