add 2nd baseline to tracking Gantt view

J

Jim Aksel

Hello David - Try View/More Views... and then select Multiple Baselines Gantt
chart.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 