We have encountered an inconsequence of Project behavior.
When we add new field to Resource sheet view the project automatically:
1. Creates new local "Entry" table
2. Creates new local " Resource sheet " view
3. Allows saving the changes and dispays the new field after project reopening
When we're trying to make the same changes in Gantt char view, the project
notifys that it won't be saved and doesn't dispay it after project reopening.
In this case we're forced to create new table and new view with different
names and then to insert new field.
On the other hand, during MS Project Pro 2003 course we have tried to make
the same changes on the library computer and so Gantt char view has behaved
exactly as Resource sheet (allowed to add new field and created new table and
view automatically).
So my question is, how can we make Gantt char view behaves like Resource
sheet as it happened on the library computer ?
When we add new field to Resource sheet view the project automatically:
1. Creates new local "Entry" table
2. Creates new local " Resource sheet " view
3. Allows saving the changes and dispays the new field after project reopening
When we're trying to make the same changes in Gantt char view, the project
notifys that it won't be saved and doesn't dispay it after project reopening.
In this case we're forced to create new table and new view with different
names and then to insert new field.
On the other hand, during MS Project Pro 2003 course we have tried to make
the same changes on the library computer and so Gantt char view has behaved
exactly as Resource sheet (allowed to add new field and created new table and
view automatically).
So my question is, how can we make Gantt char view behaves like Resource
sheet as it happened on the library computer ?