Add Predecessor/Successor filed in Project Center View

P

pajamasam

I have an Executive that views the Project via PWA. He asked why he wasn't
able to see any dependencies listed. Is it possible to add both the
Predecessor & Successor fields to the Project Center view? I look through the
list of availalbe fileds via admin/manage views/Project Center/modify view
but don't see an option to add this info. Help please. Thanks in advance.
 
D

Dale Howard [MVP]

Smitty --

You need to modify one of the Project task views, rather than the Project
Center views. Hope this helps.
 