I would appreciate help from someone in adding the resources Labor, Material
and Equipment to a MS Project's file and have it calculate into the BCWP
column when I do the tracking. I would like to be able to say a task is i.e.
70% complete and have it calculate the whole task, and be able to put a
dollar amount in the material or equipment column and have calculate without
it interferring with the labor of the task.
 