Is there a way to add a sub task to a task programatically?
J Jan De Messemaeker Sep 18, 2003 #2 Hi Don, Yes. First add the task: Set Nutask=activeproject.tasks.add("Name",Before=...) Nutask.outlineindent HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional Project Management Consultancy Prom+ade BVBA 32-495-300 620
Hi Don, Yes. First add the task: Set Nutask=activeproject.tasks.add("Name",Before=...) Nutask.outlineindent HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional Project Management Consultancy Prom+ade BVBA 32-495-300 620
J Jan De Messemaeker Sep 19, 2003 #3 Hello, taskyoujustfound.id+1 HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional Project Management Consultancy Prom+ade BVBA 32-495-300 620
Hello, taskyoujustfound.id+1 HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional Project Management Consultancy Prom+ade BVBA 32-495-300 620