Situation: fixed duration task, several resources assigned to the task, one
is finished, the rest have remaining hours.
When I extend the duration, the resources that are not complete have their
remaining hours incremented while the resource that was complete has their
actual hours incremented, remaining hours remains zero.
I would expect that all resources should have their remaining hours
incremented and that the actual hours would not be affected.
Can anyone explain the rationale behind this behavior?