Adding additional requirement infomation to enterprise generic resource assignments

G

gregdummett

Hi,

I have a question from one of my project managers that I cannot seem to

find an answer for.


We uses generic resources i.e. "VB Programmer" which are assigned to
the plan by the PM and then the Resource manage will later substitute a

real resource.


However, the PM may have additional requirements for the resource i.e
"Must be able to work on the client's site in London every Monday".


How can they impart this information to the resource manager so they
can select the correct person.


In the current process the PM's request resource using a paper form on
which thay can write these additional requirements. As you can imagine
they will not be too happy if the "new" Project Server based system
will not allow what they see as basic functionality.


All help will be appreciated


Greg
 
D

Dale Howard [MVP]

Greg --

Please do not cross-post your questions. Gary Chefetz already answered your
original question in the microsoft.public.project.server newsgroup.
 
G

gregdummett

Dale,

My apologies, I wasn't sure which would be the most appropriate forum
for my question. For a question such as this which group should I use?

Regards,

Greg
 
M

Mike Glen

Hi Greg,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top